Page 3
Feb27(Mon) -> March 3(Fri): No work done on the system, since PGE (the local utility) had to disconnect power, so the electricians could work on the fuse box and cabling in the basement. Since Dell's is a company from Eugene and AES gave them another assignment to start on, they decided to come back when PGE had time. The appointment was for 3/6 (Mon), so they worked the week from 3/6 (Mon) through 3/9 (Thu).
March 6(Mon)
March 7 (Tue)
March 8 (Wed)
March 9(Thu)
March 10 (Fri)
The Washington County inspector came by for the final inspection of the electrical work.
Next inspector to come is from ETO (the Energy Trust of Oregon) to check that the system is in order and functioning.
PGE still needs to come out and replace the meter - it seems the one they installed was just a preliminary solution.
The first two days were very cloudy and the system produced a mere 10-20kWh
per day.
(indicator for one array (1/2 of the system)
March 13 (Mon) PGE came out and installed a (digital) meter which reads out power fed into the grid as well as power consumed from the grid.
March 15 (Wed)
Len from the ETO came out for an inspection.
Looked at the system in detail and expressed how happy he is about the attention
to detail Dell's Electric paid, such as the
termination of the cables, the fact that everything was labeled, etc. He
even took pictures to show to others as examples of "how it should be done".
Like me, Len really dislikes the "spaghetti" some electricians leave behind ;).
Paul and Mike came out to install the network cabling for the inverters.